Witney
22,000sq ft
June 2023 - March 2024
About this project
We were pleased to work with a local logistics operator to deliver a new warehouse in Witney. The project involved the construction of a 22,000sq ft warehouse unit to accommodate for business growth.
The client requested a robust and functional space with additional mezzanine level, office accommodation and ample loading facilities, tailored to their requirements.
The total build took 10 months to complete inline with the client’s timescales. We provided a full construction and project management service.
Key Deliverables
-
Initial Design
-
Site Clearance and reduce to formation level
-
Foundations
-
Steel Frame
-
Installation of Lift Shaft and Precast Stairs
-
Drainage and Soak Away
-
Roof and Wall Cladding
-
Additional Mezzanine
-
Main Slab
-
Office Space Fit Out
-
Fire Alarm & Vestda System
-
Installation of Coldroom/Freezer
-
M&E works including Power Distribution, Lighting, Heating, Ventilation, and Air Conditioning
-
Roller Shutter Doors
-
Siphonic Drainage
-
Installation of Solar PV
-
Concrete Service Yard

Groundworks

Steel Frame

Mezzanine and Concrete Works

Completion